LBUSD Measure K Bonds

Naples Bayside Academy

Construction Budget: $675,000
Construction Duration: June-September 2015

Completed

Overview:
The summer project included demolition of four old portables and relocation of five newer portables from Monroe Elementary School. Also the girls' and boys' restrooms were remodeled to meet Americans for Disability Act (ADA) requirements. Construction of an ADA compliant ramp and stairs was completed at the west end of Building A.

 

Additional Information:

 

Applicable District-wide Projects

 

School Website

Elementary School Boy in Long Beach

 

Architect:
Ziemba + Prieto